Every building, driveway and retaining wall is only as good as the ground underneath it. Before a digger breaks ground on most projects, someone needs to know what that ground is made of, how much weight it can carry, and how it will behave when it gets wet. That’s the job of soil testing and the geotechnical report.
If you’re planning a build, it helps to understand what’s in that report and how your contractor uses it. It explains a lot about why foundation preparation is done the way it is, and why skipping the testing stage can cost far more than it saves.

What is a geotechnical report?
A geotechnical report is a document prepared by a geotechnical engineer (sometimes called a geo-professional) after investigating the soil and rock on a site. The investigation usually involves some combination of hand auger boreholes, test pits dug with a digger, Scala penetrometer tests and, on larger or more complex sites, machine-drilled boreholes or cone penetration testing.
The engineer then interprets those results and writes up what the ground is like, what risks it presents, and what needs to happen to make it suitable for the proposed build.
What soil testing before construction tells you
Bearing capacity
Bearing capacity is how much load the ground can safely support before it starts to compress or fail. It’s the single most important number for foundation design.
In New Zealand, standard residential foundations are designed on the assumption of “good ground”, which has a defined minimum bearing capacity. If testing shows the soil falls short of that, the foundations need specific engineering, or the ground needs to be improved before building starts. Either way, it changes what happens on site.
Groundwater
The report will note whether groundwater was encountered and at what depth. A high water table affects almost everything: how deep you can excavate without the hole filling with water, whether dewatering is needed, how stable the sides of an excavation will be, and what drainage the finished site needs.
Groundwater can also change with the seasons, so an engineer may comment on the likely winter level, not just what they found on the day.
Unsuitable soils
Not all ground is fit to build on as it sits. Common problem materials include topsoil and organic matter, peat, soft or saturated clays, expansive clays that swell and shrink with moisture, and uncontrolled fill that someone placed in the past without compaction or records.
The report will identify these layers, how deep they go, and whether they need to be removed, treated or worked around.
Slope stability and other hazards
On sloping sites, the engineer will look at whether the ground is stable and what’s needed to keep it that way. That might mean setbacks from the slope, retaining, or drainage to control water moving through the ground.

What the report recommends for earthworks
This is the part of the report that matters most to your earthworks contractor. The recommendations typically cover:
- Undercut depth: how far down unsuitable material needs to be dug out before reaching competent ground
- Cut and fill limits: how steep batters can be, and how much fill can be placed and where
- Fill specifications: what material is acceptable as fill (for example, a specific grade of hardfill or approved site-won material) and what isn’t
- Compaction requirements: the layer thickness fill must be placed in and the level of compaction each layer must reach
- Drainage: subsoil drains, cut-off drains or other measures to manage groundwater and surface water
- Inspection hold points: stages where the engineer needs to inspect before work can continue, such as viewing the base of an undercut before any fill goes back in
Who does what: the engineer’s role vs the contractor’s role
This is where people often get confused, so it’s worth being clear.
The geotechnical engineer investigates the ground, interprets the results, and sets the requirements. They decide what’s suitable, what depth is needed, what fill specification applies and what compaction standard must be met. They also inspect at the agreed hold points and, at the end, confirm that the work meets their recommendations.
The earthworks contractor carries out the work to that specification. That means excavating to the required depth, sourcing and placing the right fill, compacting it in the right layer thickness, installing drainage and calling the engineer in at each hold point.
A good contractor doesn’t redesign the engineer’s recommendations on the fly. But they do bring practical knowledge of how ground behaves once you start digging. If conditions on site don’t match the report, such as softer ground than expected, water where there shouldn’t be any, or buried fill nobody knew about, the contractor stops and flags it so the engineer can reassess. That communication between the two is what keeps a job on track.
How a contractor turns a geotechnical report into site work
Here’s what that looks like in practice on a typical job:
- Review the report before pricing. Undercut depths, fill specs and drainage requirements all affect cost, so they need to be understood before a quote goes out, not discovered halfway through.
- Strip and excavate. Topsoil and unsuitable material is removed down to the depth the engineer specified.
- Engineer inspection. The engineer checks the exposed ground to confirm it’s what they expected before anything is built on it.
- Place and compact fill. Approved fill goes back in, layer by layer, with each layer compacted to the required standard.
- Test as you go. Compaction is tested during filling to prove it meets the specification, rather than hoping it does.
- Install drainage. Any subsoil or cut-off drains are put in as specified.
- Sign-off. The engineer confirms the finished platform meets their requirements, ready for foundations.
Skipping or rushing any of those steps is where problems start. A platform that wasn’t properly compacted or had soft material left under it can lead to cracked slabs, uneven floors and settling that shows up years later.

Why it’s worth doing properly
Soil testing and a geotechnical report cost money upfront, and it’s tempting to see them as a box to tick. But ground problems are some of the most expensive to fix after the fact, because by then there’s usually a building sitting on top of them.
Knowing what’s underground before you start means an accurate quote, fewer surprises on site, and foundations that do their job for the life of the building.
Talk to Excavat before you break ground