Eltham Road Stormwater Upgrade

We undertook the Eltham Road stormwater upgrade project for South Taranaki District Council to address failing underground drainage systems at the Stock Underpass location. This project involved the complete replacement of deteriorated stormwater infrastructure at significant depth, requiring careful planning and execution to maintain public safety while upgrading this infrastructure that was essential to the local community.

Project Scope and Objectives

The primary objective was to replace a failed 24-meter section of 450mm PVC stormwater pipe running between manholes MH2 and MH1, situated at a challenging depth of at least 4 meters below ground level. The project scope encompassed several interconnected elements designed to create a comprehensive upgrade of the stormwater management system.

The core work involved excavating and removing the failed 450mm PVC pipe and replacing it with robust 450mm Class 4 concrete culvert pipe, specifically rated for the 4-meter installation depth. This upgrade addressed immediate structural failures while providing long-term durability suited to the site’s demanding conditions.

A secondary but equally important component involved removing an existing 225mm PVC pipe that created a significant bottleneck in the drainage system. This pipe was replaced with salvaged sections of the better-quality 450mm PVC pipe, effectively eliminating the flow restriction at MH1 and improving overall system hydraulic performance.

The project also included substantial civil works to address collateral damage from the pipe failures. The northern shoulder of the roadway had slumped due to the underground infrastructure problems, requiring complete reconstruction using rock materials supplied by the local landowner. Additionally, 210 square meters of damaged pavement between the excavation area and the western approach to the Stock Underpass required ripping, remaking, and resealing.

Technical Challenges and Solutions

Excavation Depth and Safety

Working at 4-meter excavation depths presented significant safety and logistical challenges. The project required careful attention to safe working batter angles and implementation of comprehensive safety controls to meet South Taranaki District Council’s stringent safety audit requirements. Standard safety measures were implemented throughout the excavation process, with continuous monitoring of ground conditions and excavation stability.

Unexpected Ground Conditions

A significant challenge emerged with the discovery of substantial organic matter including buried trees throughout the excavation area. This organic debris compromised soil integrity and created unstable ground conditions that required careful management during excavation. All organic material needed complete removal and proper disposal before pipe installation could proceed.

Material Management and Logistics

The project required careful coordination of material supply and storage, particularly given the need to salvage usable sections of the existing 450mm PVC pipe for reuse in replacing the 225mm line. This approach required on-site assessment and selection of suitable pipe sections, demonstrating efficient resource utilisation while maintaining project quality standards.

The concrete culvert pipes, rated for 4-meter depth installation, required specialised handling and installation techniques. Proper bedding and backfilling procedures were essential to ensure long-term performance and load distribution at the significant installation depth.

Project Management and Coordination

The project required full road closure coordinated by South Taranaki District Council, necessitating careful scheduling and public communication to minimise disruption to local traffic patterns. The work was planned to occur within standard working hours, with weather conditions monitored to ensure optimal conditions for both excavation and final sealing operations.

Site access management was crucial, with adequate provision for machinery operations, material storage, and laydown areas. The project team had to ensure sufficient space for the large excavation equipment required for 4-meter deep excavations while maintaining safe working conditions throughout the project duration.

Outcomes and Benefits

The project successfully replaced failing infrastructure with durable Class 4 concrete culvert pipe rated for 4-meter depth installation. Elimination of the 225mm bottleneck at MH1 significantly improved hydraulic performance, reducing future flooding risks. The reconstruction of the northern shoulder and 210m² of pavement repairs restored full road functionality and safety standards.

Contact Excavat today to discuss your next infrastructure project and discover how our expertise can help you overcome complex engineering challenges while maintaining the highest safety and quality standards.

Related Projects

St Joseph’s School Hawera

Year Complete — 2025Location — Hāwera, TaranakiHead Contractor — Clelands Construction Excavat was engaged by head contractor Clelands Construction to carry out all earthworks and civil preparation for the redevelopment of St Joseph’s School Hāwera — a project that delivered 10 new classrooms and a 2,300m² outdoor learning and play

Read More +
Foundation Preparation Project Hoiho Fonterra

Project Hoiho at Fonterra

Project Overview Fonterra’s Project Hoiho at the Whareroa site was a major undertaking focused on constructing Energy Centre 6 (EC6), a new facility housing the country’s largest heat pumps as part of a comprehensive ammonia processing plant upgrade. Excavat was contracted by Apollo Projects to deliver foundation and civil construction

Read More +

Eltham Kiwifruit Orchard

The Challenge The client needed to establish a new kiwifruit orchard on undeveloped land that presented several challenges: Our Solution Water Infrastructure & Access We relocated the existing water mains to run alongside the gravel driveway, installing a new 20mm water pipe ensure reliable water supply. The existing driveway was

Read More +

Forestry Track and Culvert Replacement

A major forestry operation experienced significant damage to a critical access road culvert due to a washout, requiring emergency replacement and track restoration. The existing log culvert structure had failed, creating a hazardous crossing point that prevented safe vehicle access to forest management areas. The damage had compromised both operational

Read More +

Ready to break ground on your project?

Contact us today for a free, no obligation quote and let's get digging!